gsoc:2009:benchmarks [2009/05/21 01:10] – brief project plan hjalle | gsoc:2009:benchmarks [2017/09/22 13:28] (current) – external edit 127.0.0.1 | ||
---|---|---|---|
Line 14: | Line 14: | ||
Late may and early June: Research and start coding on the CLI-version of the benchmark suite. This involves porting necessarily benchmarks and place them in the benchmark suite. | Late may and early June: Research and start coding on the CLI-version of the benchmark suite. This involves porting necessarily benchmarks and place them in the benchmark suite. | ||
- | Mid june - late june: The CLI version of the benchmark suite should have a clear shape. | + | Mid June: The CLI version of the benchmark suite should have a clear shape. |
- | Early July (Mid term): The CLI-application should be totally complete and work should be focused on the web applications such as phpBB, worpress, joomla and/or SugarCRM. | + | Mid June - Early July: The CLI-application should be totally complete and work should be focused on the web applications such as phpBB, worpress, joomla and/or SugarCRM. Depending on the CLI-application, |
- | Early august: Applications | + | Early July: Work on the web application |
- | August 10th - August 17th: Documentation and bug checking. | + | Early August: The first web application should be finished or almost done. |
+ | |||
+ | August 10th - August 17th: Buffert week for problems, documentation, |